Gas Drainage Remote Well Head Monitoring System
- Mining & Minerals
Gas Drainage Remote Well Head Monitoring System
Triple i completed the design, procurement, installation, setup and commissioning of remote monitoring and control equipment. The project was performed on a schedule of rates, based on a budget estimate.
Scope
- Develop electrical design and software functionality to meet customer requirements.
- Design control and instrumentation systems to meet site conditions.
- Develop Wireless Communication Network to allow access to remote site.
- Supply & Install Fibre for installation from Main PLC to Plant Network.
- Rewire and retrofit existing panels with equipment required.
- Carry out all instrumentation tubing to valves.
- Perform Hazardous Area Installation & Compliance checks.
- Integrate with existing system on site.
- Perform Site Acceptance Testing of system with customer.
Control Systems
- Allen-Bradley Logix 5000 & Point I/O over radio with Citect SCADA
- Wireless Network – Prosoft ILX2-IHW-A & ILX34-AENWG radios
Deliverables
- New controls for remote monitoring and control of equipment.
- Installation complete on time and on budget.
- Cost and performance targets were all met.
- Changeover of system & support provided during initial few weeks of operation.